PROJECT HIGHLIGHTS 2007
Risk Analysis for Aluminum Equipment
2007 - Aluminum heat exchangers were
inspected by MTS as turn-key contract. An inspection plan was constructed for
locations predicted by computational analysis. The plan for inspection addressed
insulation removal, radiography, borescope inspection. Inspection results were
interpreted to assess degree of contamination and risk of operation.

AHX Risk Analysis
|